Client:

PDO Oman

Location:

Oman

Date:

2026 – 2029

Project

Description

Increasing the gas handling capacity of BGS (from 1.4 MMSCMD to 4.2 MMSCMD) & retaining the oil handling capacity of 4000 m3/d. Oil will pass through a 3-stage separation via a new single larger-capacity train and the gas produced will be dehydrated in a large TEG unit. Gas will further route to Gas injection (GI) compressors. Existing BGS Compressors and oil storage tank/pumps will be utilized to increase the gas handling capacity.

Contract Type
EPC LSTK

Related

Projects