Client:

Petrobel

Location:

Egypt

Date:

2015 - 2017

Project

Description

Installation of Five Meg Regeneration Units (MRU) to reach a total capacity of 15.000 bbl./d of free water. The installation of the new MRU requires the upgrading of some ancillary equipment such as Lean and Rich MEG tank, Booster pumps, Injection pump, Sour Water System in addition to a suitable water disposal system.

The project has been phased considering installing:

    • Phase 1 - ASU: 2 MRU installed with production capacity of 6000 barrels per day
    • Phase 2 – RUP:3 MRU installed with production capacity of 9000 barrels per day

The installation of the new MRU requires the upgrading of some ancillary equipment such as:

  • Lean and Rich MEG tank - Phase 2
  • Booster pumps - Phase 1&2
  • Injection pump - Phase 1&2
  • Sour Water System - Phase 1&2

In addition, a suitable water disposal system will be required as well.

Contract Type
Lumpsum for Detailed Engineering, Procurement, Professional Services and Cost plus for Site Support

Scope of Work
Detailed Engineering, Procurement services and site support