Client:

Saudi Aramco

Location:

Egypt

Date:

2006 - 2009

Project

Description

Expansion of Yanbu NGL plant capacity from 390 to 585 MBOD. The work scope includes 195 MBOD de-Ethanizer with ancillaries and propane, refrigeration system, feed to the existing de-Propanizer and de-Butanizer columns, construction of substation with process interface room and expansion of DCS and ESD systems.

Contract Type
EPC LSTK (Enppi Main Contractor)

Scope of Work
Detailed engineering, material supply, construction, commissioning & start-up