Optimize the production of Abqaiq Field and hold the maximum sustainable capability (350 MBCD) and overcome the decline in the well head pressure due to the increase in the field water cut, by reducing of all HPPTs operating pressure of HPPTs at (GOSP 2 & 6) from 450 PSIG to 150 PSIG, and (GOSP 3 & 5) from 220 PSIG & 400 PSIG to 150 PSIG by installing gas compression train(s), saltwater injection pump, revamp of existing compressors and pumps, overhead power lines, and associated electrical, process automation, buildings, telecom. and utilities requirements necessary to achieve the objective.
Saudi Aramco
Saudi
2023 – 2027
Share:
Project
Description
Contract Type
EPC Main Contractor
Scope of Work
Detailed Engineering, Procurement, Construction, Pre-commissioning, and Commissioning & Startup Assistance