Developing a single six-slot platform at the Gulf of Suez with ESP, subsea 8” multiphase pipeline, subsea 6” water injection pipeline and onshore receiving facilities within SUCO Ras Badran existing facility. The expected production rate is 6,000 BOPD. The onshore receiving facilities will have a three-phase production separator, metering equipment and onshore control room. The separated fluids will be further treated onshore.

AOC
Egypt
2008 - 2009
Share:
Project
Description
Contract Type
Lump-sum for professional services – reimbursable for number of specialized studies (e.g. RAM, EIA, etc....
Scope of Work
Front End Engineering Design (FEED)