Replacement & segregation of KHUFF Gas Piping at UGP shall replace the existing stainless-steel header and branch connection piping at the KHUFF Gas Trains that is failing due to Chloride Stress Corrosion Cracking (Cl- SCC) with Cl-SCC resistant material carbon steel internally cladded with 3mm Alloy 825. The project also necessitates segregating the KHUFF Gas Trains into two independent trains which will improve operational flexibility and minimize the impact on the KSA Master Gas System.
Saudi Aramco
Saudi
2018 – 2021
Share:
Project
Description
Contract Type
EPC LSTK- Main Contractor
Scope of Work
Detailed Engineering, Procurement, Construction, Pre-commissioning and Commissioning & Startup Assistance