Client:

Suez Oil Processing Company (SOPC)

Location:

Suez

Date:

2018 - 2027

Project

Description

Rehabilitate the Coker Complex in SOPC company to increase production to reach 5000 MTBD that includes the following units:

  • Vacuum Distillation Unit “VDU” (Unit 10) - 5000 MTBD
  • Kerosene Hydro treating Unit (Unit 11) - 1500 MTBD
  • Delayed Coker Unit (Unit 12) and Vapor Recovery Unit “VRU” (Unit 14) – 3400 MTBD (both units)
  • Diesel Hydro treating Unit (Unit 13) – 5250 MTBD
  • Amine “Sweetening” Unit (Unit 15) – 400 MTBD

Some units will be revamped, and the others will be replaced.

Contract Type
Lumpsum: Professional Services (incl. Construction Supervision)
Cost Plus: Procurement Services

Scope of Work
Basic and detailed engineering, procurement services and construction supervision