Client:

Saudi Aramco

Location:

Egypt

Date:

2018 - 2023

Project

Description

Extending the existing 230kV Bus1 and installing one new disconnecting switches, an SF6 breaker, with CCVT Voltage transformers and Pot Head termination for the 230kV Underground Cable. Supply and install new generator step-up transformer 13.8/230kV and a new 13.8kV ISO-Phase bus.

Contract Type
EPC LSTK Main Contractor

Scope of Work
FEED Verification, Detailed Engineering, Procurement, Construction, and Pre-commissioning, in addition to preparation of As-built drawings as well as providing commissioning and start-up assistance activities.