Expansion of Yanbu NGL plant capacity from 390 to 585 MBOD. The work scope includes 195 MBOD de-Ethanizer with ancillaries and propane, refrigeration system, feed to the existing de-Propanizer and de-Butanizer columns, construction of substation with process interface room and expansion of DCS and ESD systems.
Saudi Aramco
Egypt
2006 - 2009
Share:
Project
Description
Contract Type
EPC LSTK (Enppi Main Contractor)
Scope of Work
Detailed engineering, material supply, construction, commissioning & start-up