Pharaonic Petroleum Company (PhPC)

2016 – 2019

Lumpsum for professional services ,Cost Plus for procurement services and reimbursable for construction supervision

The project aims to process the production from Atoll offshore field at the existing West Harbor onshore plant at Port Said with a daily production of 360 MMSCFD of gas and 15,000 BPD of condensate. The Project comprises the installation of new equipment and the modification and development of the existing facilities to accommodate the additional produced quantities.
The project scope also includes laying of a new 6” pipeline with a length of 6 km to deliver the separated condensate from West Harbor plant to El Gamil plant.